Contract 05-0R8904

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Significant amounts of brush/trees are in the work area under the bridge and will require clearing and grubbing. What do we do with the trimmings? Can they be laid to the side along the right of way, or do they have to be hauled off site?

A1) Per sections, 16-1.04 and 16-1.06 of the Standard Specifications, The trimmings and the disposal cost are the Contractor's responsibility. If changes are requested, they may be handled by proposed Contract Change Order. The Department of Fish and Game must be consulted and the 1602 permit must be complied with.


Q2) Xxxxx?

A2) Xxxxx.


Q3) Xxxxx?

A3) Xxxxx.