The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Q1) What is the bid date, November 6 or Novemeber 8? Instuctions on Bid form state bid due date as November 8 and bid opening as November 6, two days before bids are due. Please clarify.

A1) Refer to Addendum No. 1, dated October 22, 2007, which specifies the bid date as November 8, 2007. Return envelopes marked “REVISED” and showing the November 8, 2007 bid date are included.


Q)

A)


Q)

A)