California Department of Transportation
 

Contract 10-0U9204

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Is the Sand Equivalent for Shoulder Backing a minimum of 10-35 or can it exceed 35?

A1) Please refer to Section 10-1.14 "Shoulder Backing" of the Special Provisions. The Sand Equivalent requirement for shoulder backing: 1. With any combination of natural and reclaimed pavement structure (AC, PCC, LCB, CTB) is 10-35 (Para 3) 2. With any combination of natural materials is 10-30 (Para 5) 3. With 100% reclaimed AC is 10 minimum (Para 3). 12Mar11.