California Department of Transportation
 

Contract 10-0S5004

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Can the bid be postponed so that bidders will be able to go look at the project site? The work is not likely to take place until July or August. It does not seem right to bid a project that one can not go and see becasue the road is closed.

A1) Please refer to Addendum No.2, dated March 22, 2010: "Bids for this work will be opened on Tuesday, May 12, 2010, instead of the original date of Tuesday, March 24, 2010." 22Mar10


Q2) The centerline stripe quantities appear to be off. For a project that is 9.0 miles long, there is only 19,335 LF (3.67 miles) worth on Centerline. This is compared to 47,520 LF of edgeline (18.0 miles). Please advise.

A2) The location is mostly a narrow two lane highway with no centerline stripe but mostly edge line stripe. Please bid per bid package.