Description
The existing bridge, built in 1964, is approaching the end of its service life due to advancing corrosion of the deck and superstructure reinforcement (rebar) caused by routine applications of roadway de-icing salts. Caltrans is responding in an appropriate time frame to replace Sly Park Undercrossing before the level of distress reaches a point that would affect the safety or serviceability of the bridge.

Project Benefits
Replacing the structure will ensure safety to the traveling public. The project will also add sidewalks to both sides of Sly Park Road, curbs, curb ramps and gutters.

Funding Breakdown
Local - N/A
State - $7.67 million
Federal - N/A
Estimated Total Project Cost - $7.67

Project Schedule
Environmental Document Completed -- September 2009
Right of Way Acquisition Completed - -August 2013
Design Completed -- August 2013
Advertise --October 2013
Begin Construction -- April 2014
Expected Construction --
November 2014

Partnership
none

Project Contact
John Holder, Project Manager (530) 741-5448 email:john.holder@dot.ca.gov
Steve Nelson, Public Information Officer (530) 741-4566 email:steve.nelson@dot.ca.gov

project map