The following is a tentative schedule for State Highway Construction, Maintenance, and Permit projects for the week of:
July 6, 2008 - July 12, 2008
THIS SCHEDULE IS SUBJECT TO CHANGE DEPENDING ON WEATHER CONDITIONS.
NO TWO CONSECUTIVE RAMPS CLOSED AT THE SAME TIME.
|
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
|
1 |
07/07/08 - 07/10/08
C1FA |
7:00 AM - 3:30 PM |
OCEAN AVE & 12TH ST TO CENTRAL AVENUE
PM 19.25 TO 22.07 |
BOTH DIRECTIONS #2, #1 OF 2 LANES 0 - 5 MINUTE DELAY |
PAVING |
|
1 |
07/11/08
C1GA |
7:00 AM - 1:00 PM |
OCEAN AVE & 12TH ST TO CENTRAL AVENUE
PM 19.25 TO 22.07 |
BOTH DIRECTIONS #1, #2 OF 2 LANES 0 - 5 MINUTE DELAY |
PAVING |
|
101 |
07/07/08 - 07/11/08
C101QA |
9:00 PM - 6:00 AM |
ORTEGA STREET TO ANAPAMU STREET
PM 14.51 TO 14.96 |
NORTHBOUND #3 OF 3 LANES 0 - 10 MINUTE DELAY |
LANDSCAPE IRRIGATION |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
101 |
07/07/08 - 07/11/08
C101JA |
9:00 PM - 6:00 AM |
CARRILLO STREET
PM 14.76 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
LANDSCAPE IRRIGATION |
|
101 |
07/08/08 - 07/10/08
C101BF |
7:00 AM - 3:00 PM |
TAJIGUAS RANCH ENTR TO GAVIOTA STATE PARK ENTR
PM 38.78 TO 46.36 |
NORTHBOUND #1 OF 2 LANES 0 - 10 MINUTE DELAY |
GUARDRAIL INSTALL (W/RAMPS) |
|
101 |
07/07/08
C101CB |
8:00 AM - 3:00 PM |
TAJIGUAS RANCH ENTR TO GAVIOTA STATE PARK ENTR
PM 38.78 TO 46.36 |
NORTHBOUND #1 OF 2 LANES 0 - 10 MINUTE DELAY |
GUARDRAIL INSTALL (W/RAMPS) |
|
101 |
07/07/08
C101CF |
8:00 AM - 3:00 PM |
VISTA DEL MAR ROAD TO TAJIGUAS RANCH ENTR
PM 44.32 TO 38.78 |
SOUTHBOUND #2 OF 2 LANES 0 - 10 MINUTE DELAY |
GUARDRAIL INSTALL (W/RAMPS) |
|
101 |
07/08/08
C101DF |
7:00 AM - 3:00 PM |
VISTA DEL MAR ROAD TO TAJIGUAS RANCH ENTR
PM 44.32 TO 38.78 |
SOUTHBOUND #2 OF 2 LANES 0 - 10 MINUTE DELAY |
GUARDRAIL INSTALL (W/RAMPS) |
|
101 |
07/08/08
C101EF |
7:00 AM - 3:00 PM |
VISTA DEL MAR ROAD
PM 44.32 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
GUARDRAIL INSTALL (W/RAMPS) |
|
101 |
07/07/08
C101FF |
8:00 AM - 3:00 PM |
VISTA DEL MAR ROAD
PM 44.32 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
GUARDRAIL INSTALL (W/RAMPS) |
|
101 |
07/07/08
C101BA |
8:00 AM - 3:00 PM |
JCT HWY 1 TO GARDNER RANCH
PM 48.85 TO 55.81 |
NORTHBOUND #1 OF 2 LANES 0 - 5 MINUTE DELAY |
MEDIAN BARRIER |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
101 |
07/07/08
C101GA |
8:00 AM - 8:00 PM |
JCT HWY 1 TO GARDNER RANCH
PM 48.85 TO 55.81 |
SOUTHBOUND #1 OF 2 LANES 0 - 5 MINUTE DELAY |
MEDIAN BARRIER |
|
101 |
07/08/08 - 07/11/08
C101HA |
5:30 AM - 3:00 PM |
JCT HWY 1 TO GARDNER RANCH
PM 48.85 TO 55.81 |
NORTHBOUND #1 OF 2 LANES 0 - 5 MINUTE DELAY |
MEDIAN BARRIER |
|
101 |
07/08/08 - 07/11/08
C101IA |
5:30 AM - 8:00 PM |
JCT HWY 1 TO GARDNER RANCH
PM 48.85 TO 55.81 |
SOUTHBOUND #1 OF 2 LANES 0 - 5 MINUTE DELAY |
MEDIAN BARRIER |
|
101 |
07/07/08
C101IB |
8:00 AM - 4:00 PM |
ALISAL ROAD TO ALISOS CANYON ROAD
PM 52.13 TO 68.75 |
NORTHBOUND #1 OF 2 LANES 0 - 5 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/10/08
C101KB |
5:00 AM - 4:00 PM |
ALISAL ROAD TO ALISOS CANYON ROAD
PM 52.13 TO 68.75 |
NORTHBOUND #1 OF 2 LANES 0 - 5 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101LB |
3:00 AM - 2:00 PM |
ALISAL ROAD TO ALISOS CANYON ROAD
PM 52.13 TO 68.75 |
NORTHBOUND #1 OF 2 LANES 0 - 5 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101DD |
3:00 AM - 6:00 AM |
SANTA ROSA ROAD
PM 56.46 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
101 |
07/08/08 - 07/10/08
C101ED |
8:00 AM - 4:00 PM |
SANTA ROSA ROAD
PM 56.46 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101FD |
8:00 AM - 1:00 PM |
SANTA ROSA ROAD
PM 56.46 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101GD |
3:00 AM - 6:00 AM |
SANTA ROSA ROAD
PM 56.46 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101KD |
3:00 AM - 6:00 AM |
SANTA ROSA ROAD
PM 56.46 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101LD |
8:00 AM - 4:00 PM |
SANTA ROSA ROAD
PM 56.46 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101MD |
8:00 AM - 1:00 PM |
SANTA ROSA ROAD
PM 56.46 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101ND |
3:00 AM - 6:00 AM |
SANTA ROSA ROAD
PM 56.46 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
101 |
07/07/08 - 07/10/08
C101OD |
8:00 AM - 4:00 PM |
SANTA ROSA ROAD
PM 56.46 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101PD |
8:00 AM - 1:00 PM |
SANTA ROSA ROAD
PM 56.46 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08
C101RB |
8:00 AM - 4:00 PM |
SANTA ROSA ROAD
PM 56.46 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/10/08
C101UB |
8:00 AM - 4:00 PM |
SANTA ROSA ROAD
PM 56.46 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101VB |
8:00 AM - 1:00 PM |
SANTA ROSA ROAD
PM 56.46 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101AC |
8:00 AM - 4:00 PM |
JCT HWY 246
PM 57.12 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101AD |
8:00 AM - 1:00 PM |
JCT HWY 246
PM 57.12 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101BD |
8:00 AM - 1:00 PM |
JCT HWY 246
PM 57.12 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
101 |
07/08/08 - 07/11/08
C101CD |
3:00 AM - 6:00 AM |
JCT HWY 246
PM 57.12 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101ID |
8:00 AM - 4:00 PM |
JCT HWY 246
PM 57.12 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101JD |
8:00 AM - 1:00 PM |
JCT HWY 246
PM 57.12 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101NC |
3:00 AM - 6:00 AM |
JCT HWY 246
PM 57.12 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101UC |
3:00 AM - 6:00 AM |
JCT HWY 246
PM 57.12 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101VC |
8:00 AM - 4:00 PM |
JCT HWY 246
PM 57.12 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101WC |
8:00 AM - 4:00 PM |
JCT HWY 246
PM 57.12 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
101 |
07/08/08 - 07/10/08
C101XC |
3:00 AM - 6:00 AM |
JCT HWY 246
PM 57.12 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101YB |
8:00 AM - 1:00 PM |
JCT HWY 246
PM 57.12 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101ZC |
3:00 AM - 6:00 AM |
JCT HWY 246
PM 57.12 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101BC |
8:00 AM - 1:00 PM |
DAMASSA ROAD
PM 57.55 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101CC |
3:00 AM - 6:00 AM |
DAMASSA ROAD
PM 57.55 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101DC |
8:00 AM - 4:00 PM |
DAMASSA ROAD
PM 57.55 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101EC |
8:00 AM - 1:00 PM |
DAMASSA ROAD
PM 57.55 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101FC |
3:00 AM - 6:00 AM |
DAMASSA ROAD
PM 57.55 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
101 |
07/07/08 - 07/10/08
C101GC |
8:00 AM - 4:00 PM |
DAMASSA ROAD
PM 57.55 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101HC |
8:00 AM - 1:00 PM |
DAMASSA ROAD
PM 57.55 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08
C101QB |
8:00 AM - 4:00 PM |
DAMASSA ROAD
PM 57.55 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101SB |
3:00 AM - 6:00 AM |
DAMASSA ROAD
PM 57.55 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/10/08
C101TB |
8:00 AM - 4:00 PM |
DAMASSA ROAD
PM 57.55 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101WB |
8:00 AM - 1:00 PM |
DAMASSA ROAD
PM 57.55 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101XB |
3:00 AM - 6:00 AM |
DAMASSA ROAD
PM 57.55 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101ZB |
8:00 AM - 4:00 PM |
DAMASSA ROAD
PM 57.55 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
101 |
07/08/08 - 07/11/08
C101IC |
3:00 AM - 6:00 AM |
NORTH JCT HWY 154
PM 62.67 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101JC |
8:00 AM - 4:00 PM |
NORTH JCT HWY 154
PM 62.67 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101KC |
8:00 AM - 1:00 PM |
NORTH JCT HWY 154
PM 62.67 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101LC |
3:00 AM - 6:00 AM |
NORTH JCT HWY 154
PM 62.67 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101MC |
8:00 AM - 4:00 PM |
NORTH JCT HWY 154
PM 62.67 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101OC |
3:00 AM - 6:00 AM |
NORTH JCT HWY 154
PM 62.67 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101PC |
8:00 AM - 4:00 PM |
NORTH JCT HWY 154
PM 62.67 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
101 |
07/11/08
C101QC |
8:00 AM - 1:00 PM |
NORTH JCT HWY 154
PM 62.67 |
SOUTHBOUND FULL OFF RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/08/08 - 07/11/08
C101RC |
3:00 AM - 6:00 AM |
NORTH JCT HWY 154
PM 62.67 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101SC |
8:00 AM - 4:00 PM |
NORTH JCT HWY 154
PM 62.67 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101TC |
8:00 AM - 1:00 PM |
NORTH JCT HWY 154
PM 62.67 |
SOUTHBOUND FULL ON RAMP CLOSURE 0 - 10 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/10/08
C101NB |
8:30 AM - 10:00 PM |
ALISOS CANYON ROAD TO ALISAL ROAD
PM 68.75 TO 52.13 |
SOUTHBOUND #1 OF 2 LANES 0 - 5 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/11/08
C101PB |
8:30 AM - 3:00 PM |
ALISOS CANYON ROAD TO ALISAL ROAD
PM 68.75 TO 52.13 |
SOUTHBOUND #1 OF 2 LANES 0 - 5 MINUTE DELAY |
ROADWAY REHABILITATION |
|
101 |
07/07/08 - 07/11/08
M101MA |
9:15 AM - 3:30 PM |
ALISOS CANYON ROAD TO CLARK AVENUE
PM 68.75 TO 82.18 |
NORTHBOUND #2 OF 2 LANES 0 - 10 MINUTE DELAY |
SHOULDER WORK |
|
101 |
07/07/08 - 07/11/08
C101BB |
9:00 PM - 6:00 AM |
SANTA MARIA WAY
PM 84.34 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 5 MINUTE DELAY |
BRIDGE REPAIR |
|
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
|
101 |
07/07/08 - 07/11/08
C101EB |
9:00 PM - 6:00 AM |
SANTA MARIA WAY
PM 84.34 |
NORTHBOUND FULL OFF RAMP CLOSURE 0 - 5 MINUTE DELAY |
BRIDGE REPAIR |
|
101 |
07/07/08 - 07/11/08
C101RA |
9:00 PM - 6:00 AM |
SANTA MARIA WAY TO SAN LUIS OBISPO CO LINE
PM 84.34 TO 90.99 |
BOTH DIRECTIONS #2, #1 OF 2 LANES 0 - 5 MINUTE DELAY |
SHOULDER WORK |
|
101 |
07/07/08 - 07/11/08
C101VA |
9:00 PM - 6:00 AM |
STOWELL ROAD
PM 87.52 |
NORTHBOUND FULL ON RAMP CLOSURE 0 - 5 MINUTE DELAY |
SHOULDER WORK |
|
101 |
07/07/08 - 07/11/08
C101ZA |
9:00 PM - 6:00 AM |
MAIN STREET
PM 88.6 |
BOTH DIRECTIONS PARTIAL OFF RAMP CLOSURE (#1 OF 2 LANES) 0 - 5 MINUTE DELAY |
SHOULDER WORK |
|
154 |
07/08/08 - 07/09/08
C154HD |
8:30 AM - 4:00 PM |
PARADISE ROAD TO COLD SPRING CYN BRIDGE
PM 21.59 TO 22.96 |
BOTH DIRECTIONS #1 OF 2 LANES 0 - 10 MINUTE DELAY |
STRIPING/MARKING |
|
154 |
07/08/08 - 07/09/08
C154ID |
10:00 PM - 5:00 AM |
PARADISE ROAD TO COLD SPRING CYN BRIDGE
PM 21.59 TO 22.96 |
BOTH DIRECTIONS #1 OF 2 LANES 0 - 10 MINUTE DELAY |
MEDIAN BARRIER |
|
154 |
07/10/08
C154JD |
8:30 AM - 4:00 PM |
PARADISE ROAD TO COLD SPRING CYN BRIDGE
PM 21.59 TO 22.96 |
BOTH DIRECTIONS #1 OF 2 LANES 0 - 10 MINUTE DELAY |
EARTH WORK |
|
HWY |
DATE |
TIME |
LOCATION |
IMPACT ON TRAFFIC |
PURPOSE |
|
166 |
07/07/08 - 07/11/08
C166SH |
6:30 AM - 5:00 PM |
3 MILES EAST OF COTTONWOOD CANYON ROAD
PM 55 TO 74.72 |
BOTH DIRECTIONS INTERMITTENT ONE-WAY TRAFFIC CONTROL 0 - 15 MINUTE DELAY |
EARTH WORK |
|
192 |
07/07/08 - 07/12/08
M192PA |
9:00 AM - 4:00 PM |
LA CUMBRE ROAD TO TORO CANYON/FOOTHILL
PM 0.74 TO 13.11 |
BOTH DIRECTIONS ONE-WAY TRAFFIC CONTROL 0 - 5 MINUTE DELAY |
TREE TRIMMING |
|
225 |
07/07/08
P225NA |
9:00 AM - 3:00 PM |
CAMINO CALMA
PM 2.62 |
BOTH DIRECTIONS #1, #2 OF 2 LANES 0 - 3 MINUTE DELAY |
GROUND MONITORING WELLS |
|
192 |
07/10/08
P192TB |
9:30 AM - 2:30 PM |
MOORE ROAD TO RANDALL DRIVE
PM 9.36 TO 9.48 |
BOTH DIRECTIONS #1 OF 1 LANE 0 - 5 MINUTE DELAY |
UTILITY WORK |
|
225 |
07/08/08
P225MA |
12:00 PM - 3:30 PM |
CASTILLO ST/MONTECITO
PM 4.5 |
WESTBOUND #2 OF 2 LANES 0 - 3 MINUTE DELAY |
GROUND MONITORING WELLS |
REMEMBER - THERE ARE PEOPLE OUT THERE WORKING HARD TO MAKE YOUR COMMUTE EASIER. TO PROTECT THEIR LIVES AND YOURS, SLOW FOR THE CONE ZONE! For statewide highway information call - 1-800-427-7623 (ROAD), 24 hours a day. For Internet access - www.dot.ca.gov/dist05/
# # #