Long-Term Closures of Northbound I-405 Connectors to Eastbound and Westbound I-105

Project Description:

HAWTHORNE - The California Department of Transportation (Caltrans) closed the connector ramp from northbound I-405 (San Diego Freeway) to westbound I-105 (Century / Glenn Anderson Freeway) at 10 p.m. on January 2, 2018. The ramp is expected to remain closed until the end of April 2018. Construction crews may work up to seven days per week, 12 hours per day from 7 a.m. to 7 p.m. through the end of April. There will be occasional overnight construction. Expect noise from the demolition work, machinery and construction vehicles during this time.

The work involves reconstructing distressed roadway and the embankment along the connector. Crews will excavate pavement to place geo fabric to further help stabilize the slope, install a new drainage system and repave the roadway with concrete slabs to enhance safety and create a smoother drive for motorists. This long-term connector closure is necessary to provide a safe work zone for construction crews and motorists.

The northbound I-405 connector to eastbound I-105 was closed for 14 weeks for reconstruction. It re-opened at 5 a.m. on January 3, 2018. This ramp will be closed again overnight on the following dates to allow removal of concrete debris and pouring of new concrete: from 10 p.m. to 5 a.m. the nights of Feb. 05, Feb. 06, Feb. 08, Feb. 12 and Feb. 13.

Westbound Detour Route:

From northbound I-405, exit onto Imperial Highway or Century Blvd. westbound. Drivers on the northbound I-405 originating from points south of I-110 (Harbor Freeway) are advised to take northbound I-405 to northbound I-710 or northbound I-110 to westbound I-105 into LAX.

 

 

Eastbound Detour Route:

From northbound I-405, exit Imperial Highway, drive east to arrive at I-105 at the Freeman Ave. on-ramp.
 

 

Detour signs will be posted. Motorists should anticipate delays, and are encouraged to plan ahead
and use alternate routes. For real time freeway traffic information, please visit Caltrans
Quickmap:
http://quickmap.dot.ca.gov/

Photos: Rebuilding northbound I-405 connector to westbound I-105

 

 

 

 

 

 

The long-term connector closure is part of a $4.3 million roadway and embankment repair project on both connectors of I-105, in the cities of Hawthorne and El Segundo. Griffith Company is the contractor on this project which began in March 2017, and is expected to complete fall, 2018. Caltrans reminds motorists to
"Be Work Zone Alert."

Total Programmed Project Costs:$4.385 Million

Project Contact:

Marc Bischoff
Public Information Officer
213.897.0303
Marc.Bischoff@dot.ca.gov
Twitter: @CaltransDist7
 

Connect With District 7

District 7 Blog        

Contact Information

General Information:

Phone: (213) 897-3656
Fax: (213) 897-3836

Physical Address:

California Department of Transportation
District 7
100 South Main Street
Los Angeles, CA 90012

Caltrans Logo

Translate.