Contract 10-1L980(10A2499)

The responses to bidder's inquiries, unless incorporated into a formal addendum to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Q1)  I have a question regarding bid item #11, compost at 199CY.   My erosion control sub, is stating this qty. is 4 times over what it should be with 1” coverage.  He shows a qty. of compost needed to be 49.95CY of compost for 16,117SF of dry seed.  Please review and let me know.

A1)  Total Compost should be 49.5CY.